The following is an update of the major seawall related tasks that Cardno is currently working or have
worked on recently.
Performed onsite inspections for upland repair claims at several properties.
Coordinated and prepared inspection memos regarding upland repair claims.
Finalized contractor work agreement for weep hole installation at emergency lots.
Contractor work is currently underway. Estimated completion is December 1, 2017.
Finalized contractor work agreement to stabilizing restrictor wall adjacent to Sea Trout
Place. Contractor is currently mobilizing for work. Estimated completion is December
15, 2017.
Responded to Contractor questions regarding emergency seawall repairs (new FRP
sheet piles and concrete cap) and issued minor revisions to address concerns. Bid prices
are due this week. Approximately 4 weeks are anticipated for contract negotiations,
material orders, and mobilization with construction to follow.
Design Build Request for Proposals are due January 12, 2018