Pool Slide and Tower Update

The following is a summary of the Pool Slide and Tower timeline.

Pool Slide and Stairs

  • Per the contract the pool slide and stairs contractor began construction on 11‐6‐17.
  • From 11‐6‐17 the contractor has 49 days to complete the project.
  • For work past the 49 days the contractor will be billed $200 per day up to $5,600.
  • Based on 49 days from 11‐6‐17 the project is schedule to be complete on December 25, 2017.

Pool Tower

  • Per the contract the pool slide and stairs contractor begin construction date is 11‐27‐17.
  • From 11‐27‐17 the contractor has 70 days to complete the project.
  • For work past the 70 days the contractor will be billed $200 per day up to $5,600.
  • Based on 70 days from 11‐27‐17 the project is schedule to be complete on February 5, 2018.

 

Please keep in mind there will be a pool closure of 1 or 2 days for some of the work required on the slide.

Residents will be given notice.